When does the progress payment for the “Project completion” get triggered? Will there be a case where I must make this payment and I am unable to make use of the property to rent, i.e., Certificate of Occupancy and use is not yet obtained
The Project Completion Invoice is triggered when you choose to take occupancy.
We will have a walkthrough with you and handover the project.
When this occurs, you will have the choice to either take occupancy, and we will rectify any defects.
Or
You may choose to wait until the defects are resolved and when they are complete, the invoice will be provided.
We will lodge the application for the Certificate of Occupancy immediately after the walk through. This is a government process which on average takes three weeks to be completed and the Certificate of Occupancy to be issued after handover. For investment properties, this is a good period for advertising your property.