The building line is a line drawn parallel to the front boundary that touches / runs along the face of the part of the building closest to the front boundary.
For the purpose of this definition, "building" includes:
- any external wall, or
- any terrace, landing, porch, balcony, deck or verandah that is either above 1.5m from finished ground level or covered by a roof.
"building" excludes fences, courtyard walls and retaining walls of any height,
It is not defined with reference to the setback. In other words, the building line can be in front of the front boundary setback if the Department approved of an encroachment into the front boundary setback.
Effect on the Front Zone
In the instance where the building line is closer to the front boundary than the front boundary setback, the front zone is the area between the front boundary and the building line.
Where the building line is further away from the front boundary than the front boundary setback (i.e. there is no encroachment), the front zone is the area between the front boundary and the front boundary setback.
Effect on the Primary Building Zone
In the instance where the building line is closer to the front boundary than the front boundary setback, the primary building zone is the area between the building line and a line drawn parallel to the building line 12m back.
Where the building line is further away from the front boundary than the front boundary setback, the primary building zone is the area 12m back from the front setback.
QAID 749 · last reviewed 6 October 2022
Related questions
- Can you subdivide a block with a secondary residence on it?
- What is a Letter of Authorisation?
- When is Demolition application required?
- Can a customer/property owner request a preliminary meeting with the Conservator of Flora and Fauna to ascertain if there are any special requirement's regarding trees on their property?