What is an exempt development and the BA process?
What the law says
An exempt development is building work that does not need a Development Approval (DA) because it meets all the exemption rules made under the Planning Act 2023 (A2023-18). For an extension to a single dwelling, that means complying with every rule in the Single Dwelling Housing Development Control, the relevant District Controls and the general exemption criteria. If your project needs a lease variation, it needs a DA even if it otherwise complies. A Secondary Residence always needs a DA.
Exempt from DA does not mean no approval at all. Building work still needs Building Approval (BA) under the Building Act 2004 (A2004-11), unless the work is itself exempt from BA. If a project is compliant except for one minor breach of a setback, building or solar envelope, or minimum private open space rule, an exemption declaration can be sought instead of a DA. BA is still needed after that.
How we do it
BA is the technical check that your project complies with the National Construction Code and is suitable to build. It is not a planning check. A private building certifier assesses it. The process is:
1. Appoint a licensed building surveyor as your certifier.
2. Apply for building approval and pay the relevant fees.
3. Employ a licensed builder.
4. Pay the relevant fees to the ACT Government.
Depending on the project, the BA documents can include architectural plans, structural engineering plans, energy reports, a site classification report and drainage plans. We prepare these with you and take them to the certifier.
QAID 531 · last reviewed 23 November 2026
Related questions
- Can you subdivide a block with a secondary residence on it?
- What is a Letter of Authorisation?
- When is Demolition application required?
- Can a customer/property owner request a preliminary meeting with the Conservator of Flora and Fauna to ascertain if there are any special requirement's regarding trees on their property?