What happens if I refuse to make payment?
Non-Payment, Suspension of Works, and Termination
If a progress payment is not made when due, CGFB may suspend building works by issuing written notice to the client. If payment is made within 5 business days of the notice, CGFB will resume works within a reasonable timeframe thereafter, subject to availability and scheduling.
If 10 business days pass without payment following the notice of breach, CGFB may terminate the contract by providing written notice via mail.
Upon termination, the client will be liable to pay:
- The value of all building work completed to date;
- The cost of materials already ordered or delivered;
- The cost of demobilisation and site shutdown;
- The builder’s margin; and
- Any other losses or expenses reasonably incurred by CGFB as a result of the termination.
Additional Rights for Non-Payment
In the event of late or non-payment, CGFB reserves the right to:
- Charge interest on overdue amounts at the rate prescribed under the contract or, if unspecified, the prevailing rate under the Civil Law (Wrongs) Act or applicable legislation;
- Delay the project schedule to accommodate the impact of the suspension and rescheduling of trades, suppliers, and resources;
- Recover any administrative or legal costs incurred in enforcing the contract.
Dispute Resolution
CGFB seeks to resolve all disputes promptly and amicably. However, in the event of continued non-payment, CGFB reserves the right to refer the matter to the relevant court or tribunal for formal resolution.
QAID 866 · last reviewed 21 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?