What are some of the Fees associated with Department rejections and resubmitting applications?
If the Department is not convinced the project satisfies the setback criteria, the following may happen before they reject the application:
- They make a s 141 request for further information: no fee, they will need evidence of development in similar proximity to the fence in the surrounding area.
- They make a s 144 request for DA amendment: no fee, they will need changed plans.
- They advise they will reject unless we make a s 144 application: $330.95, plus notification fees if the change is required ($1, 298.50 for major (if major change), $321.50 (if minor)).
There is no guarantee that the Department will approve the project after these requests. If they reject the application:
- We make a s 191 application for reconsideration: $357.20.
These are just the expenses associated with resubmitting the application at various points. This does not include any application to ACAT that may be made, any architect’s hours required to amend plans, etc.
QAID 793 · last reviewed 11 August 2023
Related questions
- Can you subdivide a block with a secondary residence on it?
- What is a Letter of Authorisation?
- When is Demolition application required?
- Can a customer/property owner request a preliminary meeting with the Conservator of Flora and Fauna to ascertain if there are any special requirement's regarding trees on their property?