The project has not been finished as there are still defects in the build. Why am I receiving a project completion invoice?
- We believe that practical completion is agreed when CGFB and the customers sign the Customer Project Walkthrough Document. We believe that this document fulfills the two requirements that satisfy project completion under the contract – ‘means that the building works have reached the stage where the builder certifies that they have been completed in accordance with the contract, except for minor omissions and, where applicable, has done all that the builder is except for minor omissions and, where applicable, has done all that the builder is required to do under the contract to enable a certificate of occupancy to be obtained’. There are three elements here: we are required to give notice certifying that practical completion has been achieved; there is nothing more than minor omissions; and we have done all that is required to enable a certificate of occupancy to be obtained.
- Wireton Holdings Pty Ltd v Brendon Dean Price [2011] ACTSC 65 assessed the issue of whether practical completion had been achieved. The claimed incomplete and defective works included: glass not being installed, painting being defective, some cracks and stains, the sauna door not being as specified, the air conditioning diffusers missing, a variation of the car parking spaces. All of these were considered minor defects. Similarly, when the walkthrough is signed, these outline what we consider (and you signed in agreement) minor defects that do not hinder practical completion being reached.
- There is a power under the contract for us to declare that practical completion has been achieved as allowed by clause 23.1 and that does not depend on the client signing the form. However, we care about your satisfaction and therefore have the project walkthrough document signed in good faith.
- In some cases, there will be notes in the walkthrough document that allow for the final invoice to be modified (e.g. a deduction in the amount invoiced until a condition is met). However, this document still states that practical completion has been achieved.
- We would also like to note that some defects will be outside our scope - in these cases, we are not responsible for rectifying these.
QAID 965 · last reviewed 29 July 2025
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?