So we want to do this and we know that we need to pay the LVC, which is $40k per block but we want to know when that money is due. Do we need to pay this before building or after?
Once the Territory Planning Authority (the authority) gives consent to change the Crown Lease then the charge will be issued
After the DA is approved and the Lease Variation Charge is calculated, you will get a Notice of Assessment if you're the applicant or lessee. The Notice of Assessment includes the charges to vary the Crown lease. The Notice also gives payment options and provides options to review the decision.
The crown lease will not be varied until the amount is paid; therefore, work cannot commence before payment to vary the lease. Typically Lease Variation Charges are paid at the same time as Development Applications fees following the Completeness Check of documents.
QAID 898 · last reviewed 21 November 2026
Related questions
- Can you subdivide a block with a secondary residence on it?
- What is a Letter of Authorisation?
- When is Demolition application required?
- Can a customer/property owner request a preliminary meeting with the Conservator of Flora and Fauna to ascertain if there are any special requirement's regarding trees on their property?