Practical completion in the HIA agreement - can you explain what this actually means?
In our HIA agreement, practical completion means that the building works have reached the stage where we, the builder, certify that they have been completed in accordance with the contract, except for minor omissions. Where applicable, it also means we have done all that we are required to do under the contract to enable a certificate of occupancy to be obtained.
Practical completion is formally reached when we and you sign the Customer Project Walkthrough. Minor omissions or defects noted at the walkthrough do not stop practical completion being reached.
Practical completion is not the same as having the certificate of occupancy. The ACT Government issues the certificate. Your appointed private building certifier manages the process and lodges the application. This happens after practical completion and takes approximately three weeks, subject to government processes.
QAID 301 · last reviewed 21 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?