On what grounds do we not have to pay progress payments?
Progress payments must be paid as the invoice is issued. The issuing of an invoice is considered a written claim for the progress payment. The owner must make payments upon completion of the stage. For the purposes of the HIA agreement minor ommisions to completion still qualify as completion. The only grounds to not pay progress payments is if there is a significant fault in the completion that would prohibit the stage from being functional for purpose or a major omission in that progress stage,.
QAID 862 · last reviewed 21 November 2026