For water:
Separate unit metering under a single service tie is mandatory. Separate service ties for water supply is not mandatory but can be done.
Utilities (Technical Regulation) (Water and Sewerage Code) Approval 2024 took effect as of 01 July 2024.
It is stated in Schedule 2 Subsection 5) that:
Mandatory unit metering is to commence for all new multi-unit developments where the Development Application is lodged on or after 1 July 2025.
For electricity:
Separate unit metering under a single service tie is mandatory. Separate service ties for electricity supply is not mandatory but can be done.
EvoEnergy set out the requirements for connecting electrical or gas equipment to their distribution networks in their Service and Installation Rules Manual.
It is stated subclase 5.3.5 that:
Separate services for dual occupancy/subdivision will be provided. However, where a separate service is installed to an additional premise, the cost of the second service is to be borne by the customer including any other network modification required. Evoenergy will determine the appropriate point for the connection of the service to each premise.Separate services for dual occupancy/subdivision will be provided. However, where a separate service is installed to an additional premise, the cost of the second service is to be borne by the customer including any other network modification required. Evoenergy will determine the appropriate point for the connection of the service to each premise.
QAID 1027 · last reviewed 21 November 2026
Related questions
- Can you subdivide a block with a secondary residence on it?
- What is a Letter of Authorisation?
- When is Demolition application required?
- Can a customer/property owner request a preliminary meeting with the Conservator of Flora and Fauna to ascertain if there are any special requirement's regarding trees on their property?