Questions & Answers › About Secondary Residences
If a residence has two separate utility meters, can a secondary residence have a third meter?
Icon Water:
To achieve separate metering for Water supply, one main meter would be required for the entire property. Subsequent meters for each premise will be distributed via the main meter. This allows you to measure usage for different dwellings on the same land. This process would involve seeking Hydraulic Engineer advice.
Jemena Gas/EvoEnergy:
This set up can be created. What is called a Path Valve will need to be installed on the block, which each meter would then connect to. This allows for three meters to be installed on the block, for existing residence and secondary residences.
EvoEnergy (Electricity):
Typically only one service can be provided to a block, but there are instances in which this can be changed. The new meter will need to be installed in the Primary Meter box if an additional meter is desired and approved. This may require a Service Mark, which is EvoEnergy giving permission to allow for a change in equipment on site. This will be identified by them in the approvals process.
CGFB is happy to aid in enquiries about attaching additional meters to projects.
QAID 222 · last reviewed 18 November 2026