I am entitled to liquidated damages as the project was delayed in reaching practical completion.
- There are a couple of factors to consider when making this claim. Firstly, the contract allows us a certain number of WORKING days to finish the project. In turn, only working days are considered when delays occur.
- Furthermore, at CGFB, we work to ensure that our clients are informed of any delays. This occurs through time delay letters, emails with those time delay letters, and letters to your letter box. These letters will always include the following – the date on which the letter was sent, the number of working days delayed, and the reasons for this delay. This gives us additional days for the project.
- Thirdly, if any progress payment is late, Clause 12 Item 3 states that, ‘if the owner does not make a progress payment or any payment after it becomes due, the builder is entitled to’ interest on the unpaid amount and to suspend the building works. In none of our projects have we ever suspended work – this is done in good faith, and we trust that payment will come through. We do, however, maintain the right to apply interest on that late payment as well as add days to reaching practical completion.
- In these cases, we would request evidence of this to be shown. We are open to discussing this query with you. Please email contracts@cgfb.com.au for any concerns regarding this.
QAID 964 · last reviewed 29 July 2025
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?