How long is a Development Approval (DA) valid for?
In the ACT, a Development Approval (DA) is generally valid for:
- 3 years to commence the approved development, unless otherwise stated in the approval conditions.
This means construction or approved works must substantially commence within the approval period, otherwise the DA may expire.
Important considerations
The exact validity period can vary depending on:
- The approval conditions
- The type of development
- Whether staged approvals apply
- Legislative changes at the time of approval
In some situations, extensions or amendments may be possible, however this is not guaranteed.
Why timing matters
Even if a DA is still technically valid, delays can create complications such as:
- Changes to planning legislation
- Updated building code requirements
- Expired consultant reports
- New tree or environmental requirements
- Changed service authority conditions
- Increased construction costs
For this reason, projects are generally easier to progress when approvals, documentation, and construction planning remain current and coordinated.
It is also important to understand that a valid DA does not remove the requirement to obtain Building Approval (BA) before construction can commence.
QAID 1041 · last reviewed 28 May 2026
Related questions
- Can you subdivide a block with a secondary residence on it?
- What is a Letter of Authorisation?
- When is Demolition application required?
- Can a customer/property owner request a preliminary meeting with the Conservator of Flora and Fauna to ascertain if there are any special requirement's regarding trees on their property?