Encumbrances, covenants and easements- Clause 4 HIA Agreement:
Clause 4 of the HIA Agreement puts the duty to find and disclose these matters on the owner. This is how our contract and process work. It is not a rule set by planning law.
We have completed all the research legally available to us to lodge plans. We are confident in our approach to planning approvals, but the final decision rests with the relevant authority.
The owner is the person best placed to know what is registered against the land. Encumbrances, covenants, easements and caveats are usually listed in the contract of sale.
What we need from you: please give us the details of any easements, covenants, encumbrances and caveats in writing, so our building team has them.
Why it matters: if something that could have been avoided by giving us the documents disturbs the time or price of the build, the homeowner is accountable for it.
Utility easements: you can check your block on ACTmapi's utility infrastructure map. Some easements do not show there, so a site survey may sometimes be needed. The owner of a utility easement decides its own requirements for work near it, and those decisions cannot be reviewed.
QAID 299 · last reviewed 21 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?