Does DA come first or BA come first?
In most residential projects in the ACT, Development Approval (DA) comes first, followed by Building Approval (BA).
Development Approval (DA)
DA is the planning approval stage.
This assesses whether the proposed development complies with planning rules, including:
- Setbacks
- Building height
- Plot ratio
- Crown lease requirements
- Tree protection
- Parking and access
- Neighbour impacts
- Site planning controls
This approval is typically issued by the ACT planning authority.
Building Approval (BA)
BA comes after DA and focuses on whether the project can actually be constructed in compliance with the Building Code and technical requirements.
This stage involves:
- Structural engineering
- Energy efficiency
- NCC compliance
- Waterproofing
- Drainage
- Fire safety
- Construction detailing
- Buildability
Building Approval is generally issued by a private certifier.
Important distinction
A project can receive Development Approval but still require significant changes before Building Approval can be obtained.
This is why DA approval alone does not always guarantee:
- Construction feasibility
- Final construction cost
- Structural compliance
- Full code compliance
For more complex projects, both planning and building compliance should be considered early in the design process to reduce delays, redesigns, and unexpected costs.
QAID 1033 · last reviewed 28 May 2026
Related questions
- Can you subdivide a block with a secondary residence on it?
- What is a Letter of Authorisation?
- When is Demolition application required?
- Can a customer/property owner request a preliminary meeting with the Conservator of Flora and Fauna to ascertain if there are any special requirement's regarding trees on their property?