Can I seek credit on the next progress payment as opposed to it being applied onto the final invoice?
No-progress payments are fixed amounts tied to defined stages of construction, as outlined in your HIA contract. These stage payments are not adjusted by variations (positive or negative) during the project.
If a variation results in a credit (negative amount), we issue a variation document clearly showing the amount in your favor - e.g. -$1,298 for the removal of a water tank. This credit is then applied to your final invoice, not to interim progress payments. This ensures transparent accounting and consistent payment sequencing throughout the build.
To maintain fairness and clarity, we do not apply interest to variation amounts. Interest and overdue calculations apply only to progress payments.
If you have any questions about your variation or the final balance, please contact your project manager.