Questions & Answers › Your agreement and your rights
After completion, if there are any defects pointed out, how long until these defects are fixed?
In clause 23, after completion there are 65 working days where the owner must notify the builder for defects.In addition to this we provide our guarantees listed in our proposal.
QAID 522 · last reviewed 21 November 2026
Related questions
- Home Warranty Insurance and how that works?
- Clause 10 in the HIA Agreement - Security of money
- Prime Cost Items: Will there be a margin applied on the prime cost items in the HIA Agreement?
- Clause 22. Delays and extensions of time. Mentions that the owner must chose items in sufficient time, this is not clear, what is the time frame for this?